03 · Power and planning

Where does Australia's data centre pipeline sit on the grid and in planning?

Australian data centres · as at 21 October 2026 · primer pages 19, 20, 21, 22 of 103

93 of the 143 tranches in the register's pipeline, holding 24.5 GW of its 29.3 GW of IT load where a figure is published, lie within 5 km of a transmission line of 220 kV or more (inashanu register and Geoscience Australia, as at 21 October 2026).

Of the register's 29.3 GW pipeline, where a figure is published, 24.5 GW lies within 5 km of a transmission line of 220 kV or more; distance shows where a connection is plausible and says nothing about spare network capacity (inashanu register and Geoscience Australia, as at 21 October 2026). Of the same pipeline, NSW's state significant development process holds 7.0 GW and Victoria's ministerial permits 3.2 GW, while 13.1 GW has no application on record, as at 21 October 2026.

93 of the 143 tranches in the register's pipeline, holding 24.5 GW of its 29.3 GW of IT load where a figure is published, lie within 5 km of a transmission line of 220 kV or more

The pipeline by distance to a line of 220 kV or more

The pipeline by distance to a line of 220 kV or more. Source: Geoscience Australia, Electricity Infrastructure (2026), and ABS, ASGS 2021 and LGA 2025, both CC BY 4.0; OpenStreetMap contributors (ODbL); inashanu register (21 Oct 2026). As at 21 October 2026.
DistanceTranchesIT load (MW)Share of IT load
Under 1 km4712,84044%
1 to 2 km236,58622%
2 to 5 km235,04217%
5 to 10 km312,2018%
10 to 25 km126502%
25 km or more72,0227%

A screen of proximity

Distance to a line shows where a connection is plausible; spare capacity and terms are separate questions, and the register records a connection agreement only where one is public. Median distance across the pipeline: 2.3 km.

Greater Sydney holds 6.0 GW of the pipeline's IT load, beside 0.80 GW operating; 64% of it lies in three statistical areas: Horsley Park–Kemps Creek, Prospect Reservoir and Macquarie Park–Marsfield

Pipeline by statistical area (SA2)

Pipeline by statistical area (SA2). Source: Geoscience Australia, Electricity Infrastructure (2026), and ABS, ASGS 2021 and LGA 2025, both CC BY 4.0; OpenStreetMap contributors (ODbL); inashanu register (21 Oct 2026). As at 21 October 2026.
SA2TranchesIT load (MW)
Horsley Park–Kemps Creek61,932
Prospect Reservoir71,355
Macquarie Park–Marsfield9554
Marsden Park–Shanes Park1499
Erskine Park1315
Glendenning–Dean Park1194
Lane Cove3181
St Leonards–Naremburn3130

Greater Melbourne holds 7.1 GW of the pipeline's IT load, beside 0.45 GW operating; 56% of it lies in three statistical areas: Fraser Rise–Plumpton, Mickleham–Yuroke and Laverton

Pipeline by statistical area (SA2)

Pipeline by statistical area (SA2). Source: Geoscience Australia, Electricity Infrastructure (2026), and ABS, ASGS 2021 and LGA 2025, both CC BY 4.0; OpenStreetMap contributors (ODbL); inashanu register (21 Oct 2026). As at 21 October 2026.
SA2TranchesIT load (MW)
Fraser Rise–Plumpton12,400
Mickleham–Yuroke11,000
Laverton2572
Cranbourne East–North1504
Keilor4478
Truganina–North3440
Sunshine West2308
Newport1240

Where a figure is published, NSW's state significant development process holds 7.0 GW of the register's pipeline and Victoria's ministerial permits 3.2 GW, 35% between them, while 13.1 GW (45%) has no application on record

The pipeline by consent pathway (IT load, MW)

The pipeline by consent pathway (IT load, MW). Source: EPBC Act Public Portal (read 19 and 20 Oct 2026); NSW Major Projects; Victoria, Ministerial Permits Register; inashanu register (21 Oct 2026). As at 21 October 2026.
ItemValue
NSW state significant development7008
NSW council or planning panel102
Victoria, Minister's permit (Development Facilitation Program) Victoria, Ministerial Permits Register3206
Victoria, council Victoria, Ministerial Permits Register1384
Queensland, council or Economic Development Queensland1645
WA, SA, Tasmania, the ACT and the NT2880
No application found13116

Tranches: NSW SSD 42; NSW council 5; Victoria minister 21; Victoria council 10; Queensland 6; other states and territories 14; no application 45.

Campuses referred under the EPBC Act

Campuses referred under the EPBC Act. Source: EPBC Act Public Portal (read 19 and 20 Oct 2026); NSW Major Projects; Victoria, Ministerial Permits Register; inashanu register (21 Oct 2026). As at 21 October 2026.
CampusReferralReferredLatest step
AirTrunk Mickleham campus2023/095681 Jun 2023Varied proposal accepted, 31 Aug 2026
Microsoft Honeman Close Data Centre2025/1039116 Dec 2025Considering final decision, 19 Oct 2026
Project Ares2026/1056019 Jun 2026Controlled action, 4 Sep 2026
IREN Bundey Data Centre Campus2026/1060531 Jul 2026Not a controlled action, 18 Sep 2026
Western Downs Digital Park2026/1066728 Sep 2026Referred, open for comment, 7 Oct 2026
Dover SM1B South Morang2026/1066829 Sep 2026Referred, 15 Oct 2026

Reading the referrals

A referral asks whether a project needs federal approval for its effect on matters of national environmental significance; a controlled action needs it. Each referral is read from the EPBC Act Public Portal; stage and pathway come from the planning record behind each tranche.

Stage within the two state pathways (tranches, IT load MW)

Stage within the two state pathways (tranches, IT load MW). Source: EPBC Act Public Portal (read 19 and 20 Oct 2026); NSW Major Projects; Victoria, Ministerial Permits Register; inashanu register (21 Oct 2026). As at 21 October 2026.
StageNSW tranchesNSW MWVictoria tranchesVictoria MW
Under construction111,4905365
Approved148385200
Lodged62,11682,418
Planned81,820180
Paused37452143

Sources

  1. Geoscience Australia, Electricity Infrastructure (2026), and ABS, ASGS 2021 and LGA 2025, both CC BY 4.0
  2. OpenStreetMap contributors (ODbL)
  3. inashanu register, as at 21 Oct 2026
  4. EPBC Act Public Portal, as at read 19 and 20 Oct 2026
  5. NSW Major Projects
  6. Victoria, Ministerial Permits Register

Related

The full primer is published as a 103-page PDF (download). The market model and the register behind it are licensed to firms on request; the study page lists what is published and what is licensed.

This page is one of 34 in Australian data centres: the research, indexed by the question each one answers, with the four pages where the published sources disagree set first.

inashanu publishes original research for complex decisions in markets and public policy. This primer is its study of the Australian data centre market, and commissioned work follows a published catalogue and fee schedule.

A different question? If this leaves your question open, or you would put it another way, write to research@inashanu.com. Questions that keep coming up shape what we study next.

Need this updated? Every figure here carries its date. If a decision needs it brought up to date, write to research@inashanu.com.