02 · Delivery rates and the backtest

How fast do Australian data centre projects reach operation?

Australian data centres · as at 21 October 2026 · primer pages 14, 15, 16, 17, 18 of 103

50% of the phases entering the record reached operation within four years; once construction started, 94% did, in a median of 17 months

Of the phases entering inashanu's delivery record, 50% reached operation within four years; once construction started, 94% did, in a median of 17 months, and first openings ran a median of about 50 days behind their stated targets (inashanu delivery record, as at 21 October 2026). A forecast made at mid-2021 scores no better than a flat guess and erred low, and NEXTDC's and CDC's contracted books need about 1.0 GW of new build by mid-2030, as at 21 October 2026.

74phases followed from entry (announcement or lodgement)
inashanu delivery record (21 Oct 2026); inashanu market model (21 Oct 2026)
69.6%of the entry cohort completed by the end of the record
inashanu delivery record (21 Oct 2026); inashanu market model (21 Oct 2026)
50.1%completed within 48 months of entry
inashanu delivery record (21 Oct 2026); inashanu market model (21 Oct 2026)
41 monthsnet median time from entry to operation
inashanu delivery record (21 Oct 2026); inashanu market model (21 Oct 2026)
94%completion once construction started
inashanu delivery record (21 Oct 2026); inashanu market model (21 Oct 2026)

Completion by starting point, competing outcomes counted

Completion by starting point, competing outcomes counted. Source: inashanu delivery record (21 Oct 2026); inashanu market model (21 Oct 2026). As at 21 October 2026.
CohortPhasesCompletedWithdrawnOpenNet median48 monthsFinal
Entry744492141 months50%70%
Announced643981734 months53%72%
Approved423001227 months65%100%
Construction started44390517 months94%94%

Completion incidence (Aalen-Johansen) counts withdrawal, cancellation and refusal ("withdrawn") as competing outcomes; the net median is the Kaplan-Meier duration with those outcomes censored. "Open" phases are still in progress at 21 Oct 2026. Entry is the earlier of announcement and lodgement.

What the record is, and why the model looks beyond it

The delivery record

Dated milestones for each phase of the Australian campuses that operators' disclosures and planning records describe: announcement, lodgement, approval, construction start and operation, with every withdrawal, cancellation and refusal. Phases still in progress are censored at the evidence date.

Why the model calibrates beyond it

It is a selected sample: phases of campuses that exist, mostly the large operators'. No approved phase has been withdrawn in it, so the approval cohort completes 100%. The model takes durations from the record and calibrates completion odds to population evidence (Section 01).

Completion builds slowly from entry and quickly from construction: 22% of entering phases are complete at two years, against 70% of construction starts

Share of each cohort in operation, by months since the cohort began

Share of each cohort in operation, by months since the cohort began. Source: inashanu delivery record (21 Oct 2026); inashanu market model (21 Oct 2026). As at 21 October 2026.
ItemConstruction startedApprovalEntry
0000
66.82.41.4
1220.812.24.1
1851.129.312.3
2469.741.922
3076.754.533.2
3681.965.241.5
4287.965.247.2
489465.250.1
549465.254.9
609465.256.6
669465.259.2
729476.859.2
789476.859.2
849476.862.4
909482.669.6
969482.669.6
1029482.669.6
1089410069.6
1149410069.6
1209410069.6

Incidence of reaching operation (Aalen-Johansen), in per cent. Pointwise 95% bands from a 1,000-replicate phase bootstrap are in the workbook, licensed on request (the three Followup sheets); they describe this sample, not the market.

At risk and complete, by month

At risk and complete, by month. Source: inashanu delivery record (21 Oct 2026); inashanu market model (21 Oct 2026). As at 21 October 2026.
Cohort024487296
Entry, at risk744826105
Approval, at risk42231142
Construction, at risk4413200
Entry, complete0%22%50%59%70%
Approval, complete0%42%65%77%83%
Construction, complete0%70%94%94%94%

Reading the curves

NEXTDC's and CDC's contracted books need about 1.0 GW of new build by mid-2030; at the median the model delivers 556 MW from NEXTDC and 810 MW from CDC by end-2030, above both

Disclosed delivery, new IT by period (MW)

Disclosed delivery, new IT by period (MW). Source: inashanu market model (21 Oct 2026); NEXTDC FY26 results (27 Aug 2026; release, 21 Oct 2026); Infratil and CDC Investor Day (16 Sep 2026); Bouygues Construction (30 Jul 2026); inashanu delivery record (21 Oct 2026). As at 21 October 2026.
OperatorStepFromToNew IT (MW)
NEXTDC NEXTDC FY26 results (27 Aug 2026; release, 21 Oct 2026)FY27 conversion, net of vacancyJan 2027Jun 202784
NEXTDC NEXTDC FY26 results (27 Aug 2026; release, 21 Oct 2026)FY28 conversionJul 2027Jun 2028221
NEXTDC NEXTDC FY26 results (27 Aug 2026; release, 21 Oct 2026)FY29 to FY30 conversionJul 2028Jun 2030147
CDC555 MW contract, FY28 to FY29Apr 2027Mar 2029555
AirTrunk SYD3First of five shells, at the works dateJun 2028Jun 202864

The books against what the central case delivers by end-2030 (MW)

The books against what the central case delivers by end-2030 (MW). Source: inashanu market model (21 Oct 2026); NEXTDC FY26 results (27 Aug 2026; release, 21 Oct 2026); Infratil and CDC Investor Day (16 Sep 2026); Bouygues Construction (30 Jul 2026); inashanu delivery record (21 Oct 2026). As at 21 October 2026.
OperatorPipelineBook, not yet billingNew build neededDelivered, P10 to P90Median
NEXTDC NEXTDC FY26 results (27 Aug 2026; release, 21 Oct 2026)2,641555 to 565452436 to 709556
CDC3,175555 to 750555621 to 944810
AirTrunk3,247not disclosedn/a116 to 395226

NEXTDC: binding forward orders of 555 to 565 MW (30 Jun 2026; the range is its Malaysian site), less 103 to 113 MW of built vacancy, leave 452 MW to build, so its 197 MW FY27 conversion is 84 MW of new build. CDC: its Australian 555 MW contract, up to 750 MW (the group's 1.1 GW contracted less 350 MW deployed, New Zealand included). AirTrunk publishes no book. Delivered counts all new IT, contracted or not.

Days late against the stated target, 15 first openings

Days late against the stated target, 15 first openings. Source: inashanu market model (21 Oct 2026); NEXTDC FY26 results (27 Aug 2026; release, 21 Oct 2026); Infratil and CDC Investor Day (16 Sep 2026); Bouygues Construction (30 Jul 2026); inashanu delivery record (21 Oct 2026). As at 21 October 2026.
First openingAgainst its stated target
AirTrunk SYD1On or before the target
CDC Fyshwick Campus FY2On or before the target
Equinix PE3On or before the target
Equinix SY4Late, the opening known only to a period
NEXTDC P2 Perth NEXTDC FY26 results (27 Aug 2026; release, 21 Oct 2026)Late
Equinix SY5Late
Equinix ME2Late, the opening known only to a period
AirTrunk MEL1Late
Equinix and PGIM SY9x xScaleLate
NEXTDC B2 Brisbane NEXTDC FY26 results (27 Aug 2026; release, 21 Oct 2026)Late, the opening known only to a period
NEXTDC M2 Melbourne NEXTDC FY26 results (27 Aug 2026; release, 21 Oct 2026)Late, the opening known only to a period
NEXTDC S1 Sydney NEXTDC FY26 results (27 Aug 2026; release, 21 Oct 2026)Late
NEXTDC M1 Melbourne NEXTDC FY26 results (27 Aug 2026; release, 21 Oct 2026)Late
NEXTDC S2 Sydney NEXTDC FY26 results (27 Aug 2026; release, 21 Oct 2026)Late, the opening known only to a period
NEXTDC P1 Perth NEXTDC FY26 results (27 Aug 2026; release, 21 Oct 2026)Late

One opening per campus with a stated target period; a bar where the opening is known only to a period, an open circle where it came on or before the target. The median is about 50 days; 12 of 15 opened late. The model samples this lateness for every disclosed schedule.

M3

NEXTDC now expects M3's next increase in grid supply in FY28 (21 Oct 2026). M3 puts no new IT into service before a date drawn evenly within FY28, and capacity due earlier waits for it; the completion penalty and the sampled lateness still apply.

Scored against what happened by end-2025, a forecast made at mid-2021 reaches a Brier score of 0.221, level with a flat 57% guess: no demonstrated skill yet

67rows in the source register as it stood at mid-2021
inashanu market model (21 Oct 2026); inashanu delivery record (21 Oct 2026)
41projects forecast after the strict cut-off screen
inashanu market model (21 Oct 2026); inashanu delivery record (21 Oct 2026)
26with a known outcome by 31 Dec 2025, and scored
inashanu market model (21 Oct 2026); inashanu delivery record (21 Oct 2026)
0.22Brier score of the mid-2021 method (lower is better)
inashanu market model (21 Oct 2026); inashanu delivery record (21 Oct 2026)
0.22Brier score of the flat reference
inashanu market model (21 Oct 2026); inashanu delivery record (21 Oct 2026)

Forecast against outcome, by status at mid-2021

Forecast against outcome, by status at mid-2021. Source: inashanu market model (21 Oct 2026); inashanu delivery record (21 Oct 2026). As at 21 October 2026.
Status at mid-2021ProjectsOutcome knownMean forecastCompleted
Announced6450%2 of 4
Planned15852%7 of 8
Lodged3354%2 of 3
Approved14861%5 of 8
Under construction3371%3 of 3

Mean forecast is the model's probability of operation by end-2025 from the calibration known at the cut-off; completed counts the projects found operating, in whole or in part, by 31 Dec 2025.

How the test is run

What the score says

A Brier score is the mean squared gap between a forecast probability and the outcome: 0 is perfect and a flat 50% scores 0.25. At 0.2211 against 0.2215 the mid-2021 method ranks projects no better than one flat probability, and it errs low: 19 of the 26 known projects reached operation (73%) against a mean forecast of 57%.

On capacity the backtest can match only four projects, and a national error cannot be computed: the mid-2021 operating stock is not on the public record

Matched projects: forecast against delivered IT, MW by end-2025

Matched projects: forecast against delivered IT, MW by end-2025. Source: inashanu market model (21 Oct 2026); inashanu delivery record (21 Oct 2026). As at 21 October 2026.
ItemForecast (mid-2021)Delivered by end-2025
DCI ADL02, Kidman Park2.54
Hickory Data Centres Truganina12.336
NEXTDC M3 Melbourne29.240
NEXTDC S3 Sydney48.960

Forecast is the mean simulated MW for the project at end-2025 from the mid-2021 calibration; delivered is the dated operating figure. Mean error −11.8 MW; mean absolute error 11.8 MW.

What the backtest cannot yet validate

What would make the next backtest decisive

Reading the errors

All four matched projects delivered more than forecast, by 1.5 MW to 23.7 MW: the 2021 method ramped these campuses too slowly, the same direction as its completion forecasts on page 17.

Sources

  1. inashanu delivery record, as at 21 Oct 2026
  2. inashanu market model, as at 21 Oct 2026
  3. NEXTDC FY26 results, as at 27 Aug 2026; release, 21 Oct 2026
  4. Infratil and CDC Investor Day, as at 16 Sep 2026
  5. Bouygues Construction, as at 30 Jul 2026

Related

The full primer is published as a 103-page PDF (download). The market model and the register behind it are licensed to firms on request; the study page lists what is published and what is licensed.

This page is one of 34 in Australian data centres: the research, indexed by the question each one answers, with the four pages where the published sources disagree set first.

inashanu publishes original research for complex decisions in markets and public policy. This primer is its study of the Australian data centre market, and commissioned work follows a published catalogue and fee schedule.